Weekly Construction Update, June 9
Here’s a recap of the various construction projects currently underway in Vail.
Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator
970-390-4677 or 970-479-2198; lsandoval@vail.gov
Holidays and Special Events (No Work Days)
Vail Craft Beer Classic, June 13-14
Independence Day, July 3-6
Vail Kids Adventure Games, Aug. 7-9
Labor Day Weekend, Aug. 30-Sept.1
Featured Projects
Dobson Arena Remodel
Crews continue to work on the interior of the arena, doing demo and lighting work. Inside, old lockers, offices and the former concession area have been ripped out and crews ready for new, expanded offices, locker area and concession area. Outside, crews prepare to expand the back of arena, where additional restrooms will be built. Holy Cross Energy has activated temporary transformers to get power to the building. There will be full road closures and single-lane closures of West Meadow Drive throughout the project. Please avoid the area if possible and follow all instructions given by the traffic control personnel. The project is scheduled to be completed in the fall 2026. Contractor is Hyder Construction. Town of Vail contact is John King, 970-376-0949.
|
|
Timber Ridge Village
Crews continue preparing for the start of modular-unit installation in late-June/early-July. The construction schedule is on track for crane delivery to the project site on June 20. Modular units are being delivered to the staging site in Wolcott. Crews will begin setting up jersey barriers along the northern property boundary adjacent to Lions Ridge Loop in anticipation of upslope rock fall mitigation work occurring the week of June 16. The housing project consists of a 302-unit multifamily complex. Completion is scheduled for June 2026. More information on the development and housing units can be found at www.timberridgevail.com. The developer is Triumph Development West, Coleman Wise, 970-401-5304. The site excavating contractor is Schofield Construction, Joe Haugen, 970-210-0020. The site construction contractor is Jack Hughes, Shaw Construction, 970-471-0448. Town of Vail contact is Leonard Sandoval, 970-390-4677.
West Middle Creek Housing Development, 351 N. Frontage Road
Lane and path closures for public safety are ongoing along the North Frontage Road between Middle Creek and Solar Vail. The single-lane closure will be regularly adjusted with the continuation of water main installation along the road. Flaggers remain on site to assist with traffic movement during the day (6 a.m. -10 p.m.) and traffic signals will be in place overnight (10 p.m. - 6 a.m.). Please follow traffic control signals, flagger instructions and utilize the pedestrian re-route. Expect ongoing vegetation clearing, site grading, material hauling, and delivery of the project trailer this week. Shaw Construction contact is John Payne, 303-350-1373. Town of Vail contact is Jason Dietz, 970-479-2145.
|
Here’s a recap of other construction projects currently underway in Vail.
Vail Village
The 62, 278 Hanson Ranch Road (formerly Los Amigos)
The site construction fence is up. Work includes complete renovation of the existing restaurant and prep kitchen. Contractor is RA Nelson, Jonny Cohen, 970-471-9258.
816 Forest Road Entry Bridge
Work for the Forest Road duplexes continues, including the footers, new access road and retaining walls. Approval has been granted for use of the lower lot for staging of material and equipment. General Contractor is Mexamer Construction Group, Matt Anderson,970-471-3459. Town of Vail contact is Leonard Sandoval, 970-390-4677.
304 Bridge Street
Trash and debris removal is underway during demo work. Work on the Red Lion elevator consists of adding a new two-story residential elevator for second level units and expanding existing stairs at the entry of the vestibule. Scheduled completion is mid-July. Contractor is Domoplex, Miguel Mendoza, 970-366-8512. Town of Vail contact is Leonard Sandoval, 970-390-4677.
Ford Park - South Bridge Entrance Landscape Improvements
Work north of the pedestrian bridge in Ford Park, adjacent to The Amp, will be ongoing to late June, weather permitting. Work includes landscape, irrigation and stonework. Contractor is Fitz Landscaping, James Fitz, 970-904-5233. Town of Vail contact is Kim White, 970-343-9259.
Roundabout Lighting Improvements, I-70 Vail Town Center Interchange
Work continues to complete punch list items and rejuvenation of disturbed areas. The goal of this project is to upgrade the lighting in the Vail Town Center roundabouts to meet current safety standards for both vehicles and pedestrians. The project contractor is Morton Electric of Pueblo. Town of Vail contact is Chad Salli at 970-376-2389.
Vail Art Studio, Ford Park
Construction continues on the new Vail Art Studio located on the lower bend of Ford Park, near the pedestrian bridge to Manor Vail. The Vail Art Studio is anticipated to be completed by June 30. Contractor is MW Golden Constructors, Site Supervisor Noah Green, 303-915-3393.
Vail Village Snowmelt Repairs
The majority of the work will occur along East Meadow Drive. Initial repairs, which will be completed by RH Mechanical, will not impact bus or pedestrian traffic. Town of Vail contact is Chris Delles, 970-471-2749.
Lionshead
Vail Wastewater Treatment Plant Improvements, 846 Forest Road
Eagle River Water & Sanitation District is upgrading infrastructure and the wastewater treatment process at their wastewater treatment facility in Vail. The project includes stormwater improvements, paving and landscaping with expected completion this summer. ERWSD contact is Mark Mantua, 970-401-0822.
Outlying
Red Sandstone Park Playground
The play area at Red Sandstone Park will be closed starting Monday, June 9 for painting and staining. A fence will be installed around the work area. Work is expected to be completed by June 18. Town of Vail contact is Gregg Barrie, 970-390-3286
North Frontage Road Pedestrian Safety Improvements
Crews hired by the Town of Vail will install concrete bulb outs, upgrade curb ramps, improve lighting and push button activated crosswalk flashing beacons at the North Frontage Road bus stop, in front of Safeway, to improve pedestrian visibility and shorten the crossing distance at this crosswalk. Concrete curb/gutter, ADA curb ramps and sidewalk installation is complete. Work will continue on signage and pavement marking. Town of Vail contact is Chad Salli at 970-376-2389.
East Vail Interchange
Crews will work into late June, weather permitting, on landscaping and completing irrigation work along all exit and entrance ramps of I-70 at the exit 180 interchange. Contractor is GH Daniels III and Assoc., Alan Caraveo, 970-471-5977. Town of Vail contact is Kim White, 970-343-9259.
Potato Patch Drive Water Tank Maintenance
Eagle River Water & Sanitation District is performing maintenance activities on the below-grade water tank at 756 Potato Patch Drive through June 20. Work hours are 7 a.m. to 5 p.m. Monday through Friday. Trucks and other heavy equipment will be parked on the side of the road at this location and activities may occasionally require traffic to travel in the opposite direction of the normal flow on Potato Patch Drive. Traffic control will be in place as needed throughout the project. ERWSD contact is Dan Duerr, 970-333-6773.
I-70 News
- I-70 West Vail Pass Auxiliary Lanes Project traffic holds are in effect from 9:30 a.m. to 2:30 p.m. Mondays through Thursdays. This season, CDOT has launched West Vail Pass text alerts. Text 'vailpass' (one word) to 21000. For more information visit the project page.
- Visit www.GoI70.com to sign up for their monthly e-blasts, which keep you informed on potential impacts and opportunities related to your trips on I-70. These short updates contain timely information on construction projects, new transit options, CDOT operations and strategies for beating the crowds: GoI70.com/newsletter.
Anticipated Future Projects
- First Bank, 17 Vail Road
Online Community Development Portal
Customers of the Community Development Department have access to a 24/7 online portal to submit applications for contractor registration and construction-related permits. The portal, at http://vail.onlinegovt.com/ also accepts planning applications for review by the Design Review Board and Planning Environmental Commission. In addition, residents can access the citizen portal to submit a code enforcement request or check to see the status of any permit activity in their neighborhood. To view frequently asked questions, visit http://www.vail.gov/online-services.
Email Notification Service for Contractors and Consultants
Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab at: https://public.govedelivery.com/accounts/COVAIL/subscriber/new?topic
Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for construction update emails as well as other topics, visit www.vail.gov/vailmail.