Weekly Construction Update, Nov. 24

Post Date:11/24/2025 8:00 AM

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator  
970-390-4677 or 970-479-2198; lsandoval@vail.gov  

Holidays and Special Events (No Work Days)
Thanksgiving Day, Nov. 27 – 30

Featured Projects

Dobson Arena Remodel
Following the pouring of the south footers, crews continue to work on the south walls inside the new expanded section of the arena, which will support additional stadium seating. Crews begin installing steel at the south entrance and electrical crews continue to make headway under the ice slab area. As ski season approaches, crews will tighten up construction barriers and expect there will be no full-road closures through the season. The project is scheduled to be completed in the fall 2026. Contractor is Hyder McHugh Construction. Town of Vail contact is John King, 970-376-0949.

 Crew member drains excess water found under Dobson Arena  Steel beams go up at south entrance of Dobson Arena


Timber Ridge Village
Crews began working on interior punch lists and preliminary inspections for Building A, continued stucco siding and painting on the exterior of Building A, ongoing wood siding and masonry on Buildings F and B, and framing and sheeting for the roof on Building G. Additional site work underway includes final gas service line installations as well as construction of the eastern public site staircase. There is a full road closure on Lions Ridge Loop between Savoy Villas and Moraine Drive for the installation of permanent rockfall mitigation fence above the project site. During the public safety closure, the Lions Ridge Loop bus route will operate as an out-and-back route from the Vail Transportation Center (VTC) to the Grand Traverse bus stop. The Simba Run and Sandstone bus stops on the east side will be served only by the Sandstone Route. Construction crews will not be working on Thanksgiving, Nov. 27. The Timber Ridge Village housing project consists of a 302-unit multifamily complex. Building A is planned for completion in December 2025 with the entire project planned for completion in Fall 2026. More information on the development and housing units can be found at www.timberridgevail.com. The developer is Triumph Development West, Coleman Wise, 970-401-5304. The site excavating contractor is Schofield Construction, Joe Haugen, 970-210-0020. The site construction contractor is Jack Hughes, Shaw Construction, 970-471-0448. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Timber Ridge buildings with scaffolding and crews working on siding


Southface Vail (formerly West Middle Creek) Housing Development, 351 N. Frontage RoadNewly erected soil nail wall at Southface housing development

The site continues to take shape with excavation, drilling, and spray facing progress. Crews will be working on the spray facing and finishing for building soil nail wall lift three, while continuing to drill soil nails for lift four. At the bus stop soil nail wall, drilling begins for the lower lifts. Onsite surveying work will also begin for the first cast in place retaining wall. All activities for the Southface project this fall are focused on site and utility work in preparation for next year’s construction season. Crews will not be working Nov. 27 - Nov. 30 for the Thanksgiving holiday. Shaw Construction contact is John Payne, 303-350-1373. Town of Vail contact is Jason Dietz, 970-479-2145.


Gore Creek Promenade Renewal

The flagstone walkway along the creek has been completed. Crews removed the construction fencing but replaced it with a temporary rope barrier. The park remains closed pending adequate snowpack on the uneven surfaces. Ice sculptures will return in January. Construction on this project is expected to resume in mid-April with a goal of completing the project in late June. The goal of the project is to address significant wear and tear in the popular park while improving park deficiencies such as lack of seating, improving access to Gore Creek, and ensuring the park is accessible for those with a disability or mobility impairment. The final completion date for the project will be June 26, 2026. Town of Vail contact is Gregg Barrie, 970-479-2337.

  Newly added stone steps at Gore Creek Promenade  Newly added pavers at Gore Creek Promenade


Here’s a recap of other construction projects currently underway in Vail.  

Vail Village

The 62, 278 Hanson Ranch Road (formerly Los Amigos) 
Work includes complete renovation of the existing restaurant and prep kitchen and landscaping.  Work is focused on interior work and new construction. Work will be ongoing through the fall and winter months. Current construction access is from the Vail Resorts property until the mountain opens for ski season. Deliveries of materials will occur on Hanson Ranch Road/top of Bridge Street, morning hours only during the winter months as needed with Right of Way Permit approval only.  All work is currently contained within the construction fence. The contractor is RA Nelson, Jonny Cohen, 970-471-9258. 

816 Forest Road Entry Bridge
Work on the Forest Road duplexes continues, including the footers and building foundations, new access road and retaining walls. Approval has been granted for the use of the lower lot for staging materials and equipment. General Contractor is Mexamer Construction Group, Matt Anderson, 970-471-3459. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

304 Bridge Street
Work on the Red Lion elevator consists of adding a new two-story residential elevator for second level units and expanding existing stairs at the entry of the vestibule. The scheduled completion is late November. Contractor is Domoplex, Miguel Mendoza, 970-366-8512. Town of Vail contact is Leonard Sandoval, 970-390-4677.
 

420 S. Frontage Road, Xcel Energy
Phase 2 work is currently on hold and will not be completed this fall. Completion of the project is now scheduled for the spring of 2026. Xcel Energy is doing fire valve work on Xcel property at the intersection of Vail Valley Drive and South Frontage Road. Expect shoulder and temporary sidewalk closure on South Frontage Road. Pedestrians, please follow re-routing signs. Completion date is scheduled for early November. Contractor is Blackeagle Energy Services, Xcel Energy contact is Marc Mayorga, 303-653-2346.


Outlying

Ford Park Bollard Installation Project
The Town of Vail hired Hallmark Inc. to install two retractable bollards and two fixed bollards at the top of East Betty Ford Way to control vehicular access and protect the pedestrian area. This project acts as a pilot/test project for retractable bollards within Vail. Installation of the bollards is complete. Work remains commissioning and testing of the retractable bollards. The contractor is Hallmark, Inc of Denver. Town of Vail contact is Tom Kassmel, 970-479-2235.

Potato Patch Drive Water Tank Maintenance  
Eagle River Water & Sanitation District is performing maintenance activities on the below-grade water tank at 756 Potato Patch Drive. Trucks and other heavy equipment will be parked on the side of the road at this location, and activities may occasionally require traffic to travel in the opposite direction of the normal flow on Potato Patch Drive. Traffic control will be in place as needed throughout the project. Work is expected to be complete in mid-November. The ERWSD contact is Dan Duerr, 970-333-6773.


I-70 News

I-70 West Vail Pass Auxiliary Lanes Project
The project is in winter hiatus and will resume for a final expected construction season in spring 2026. No lane closures are expected during the winter break, though minor work may take place away from the roadway. Note: the Vail Pass recreation path is not regularly maintained during the winter season. Regular maintenance will resume in the spring. 

Mountain Corridor: Golden to the Utah Border
New this winter season, CDOT has launched an online hub dedicated to the I-70 Mountain Corridor—a one-stop resource for winter driving information, road conditions, and tips for smooth, safe mountain travel. This resource brings together the best tools from COtrip.org and the COtrip Planner app in one centralized location: codot.gov/i70mountain.


 Anticipated Future Projects

  • First Bank, 17 Vail Road
  • East Lionshead Residence, 534 E. Lionshead Circle 

Online Community Development Portal

Customers of the Community Development Department have access to a 24/7 online portal to submit applications for contractor registration and construction-related permits. The portal, at http://vail.onlinegovt.com/ also accepts planning applications for review by the Design Review Board and Planning Environmental Commission. In addition, residents can access the citizen portal to submit a code enforcement request or check to see the status of any permit activity in their neighborhood. To view frequently asked questions, visit http://www.vail.gov/online-services.

Email Notification Service for Contractors and Consultants

Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab at: https://public.govedelivery.com/accounts/COVAIL/subscriber/new?topic

Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for construction update emails as well as other topics, visit www.vail.gov/vailmail.

Return to full list >>