Weekly Construction Update, Jan. 26

Post Date:01/26/2026 8:00 AM

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator  
970-390-4677 or 970-479-2198; lsandoval@vail.gov  

Holidays and Special Events (No Work Days)

President’s Weekend, Feb. 14 – 16 
Memorial Day Holiday, May 23 – 25 

Featured Projects

Dobson Arena Remodel
Inside, on the northwest side of the arena, crews demolished old concrete and added new concrete in the “ice plant” area. Crews will begin demolishing the roof in that area to make room for the installation of ice-making equipment; then, they will rebuild the roof, making it higher. Crews continue to work on concourse level steel. Fireproofing operations remain active and well-coordinated alongside the structural work. Crews have tightened up construction barriers and expect there will be no full-road closures through the ski season. The project is scheduled to be completed in the fall 2026. Contractor is Hyder McHugh Construction. Town of Vail contact is John King, 970-376-0949.    

 Crews ready northwest area for ice-making equipment.  Steel beams take shape on northwest side of Dobson


Timber Ridge Village
It's an exciting week – the first Habitat for Humanity Vail Valley closings for units in Building A (“Alpine” Building) are happening. Elsewhere on site, modular unit setting for the sixth building (Building E) continues through the end of the week. Interior unit patching and stitching is ongoing for Buildings F, B, G, and D. Garage level MEP rough-in is occurring in Buildings F and B. Solar panels are being installed on Building G and roof framing and sheeting wraps up for Building D. The Timber Ridge Village housing project consists of a 302-unit multifamily complex. Building F is expected to open in Spring 2026 and the entire project is planned for completion in October 2026. More information on the development and housing units can be found at www.timberridgevail.com. The developer is Triumph Development West, Coleman Wise, 970-401-5304. The site excavating contractor is Schofield Construction, Joe Haugen, 970-210-0020. The site construction contractor is Jack Hughes, Shaw Construction, 970-471-0448. Town of Vail contact is Leonard Sandoval, 970-390-4677.

 Interior unit patching and stitching at Timber Ridge is ongoing for Buildings F, B, G, and D.

 Interior unit patching and stitching at Timber Ridge is ongoing for Buildings F, B, G, and D.

 Garage level MEP rough-in at Timber Ridge is occurring in Buildings F and B.

Southface Vail (formerly West Middle Creek) Housing Development, 351 N. Frontage Road

Work continues on schedule. Excavation, soil nail wall drilling and spray facing continues across the site. Crews are cutting level six of the building soil nail wall and terracing to prepare for mechanically stabilized earth (MSE) and cast-in-place (CIP) retaining walls. These operations and concrete pouring will ramp up in February as the team anticipates the start of building foundation excavation. Shaw Construction contact is John Payne, 303-350-1373. Town of Vail contact is Jason Dietz, 970-479-2145.

 Drone view of construction of soil nail wall at Southface construction site.  Crews build soil nail wall a the Southface project.


Here’s a recap of other construction projects currently underway in Vail.  

Vail Village

The 62, 278 Hanson Ranch Road (formerly Los Amigos) 
Work includes complete renovation of the existing restaurant and prep kitchen and landscaping. Work is focused on interior work and new construction. Work will be ongoing through the winter months. Deliveries of materials will occur on Hanson Ranch Road/top of Bridge Street, morning hours only during the winter months as needed with Right-of-Way Permit approval only. All work is currently contained within the construction fence. The contractor is RA Nelson, Jonny Cohen, 970-471-9258.

816 Forest Road Entry Bridge
Work on the Forest Road duplexes continues, including the footers and building foundations, new access road and retaining walls. Approval has been granted for the use of the lower lot for staging materials and equipment. General Contractor is Mexamer Construction Group, Matt Anderson, 970-471-3459. Town of Vail contact is Leonard Sandoval, 970-390-4677. 


I-70 News

I-70 West Vail Pass Auxiliary Lanes Project
The project is in winter hiatus and will resume for a final expected construction season in spring 2026. No lane closures are expected during the winter break, though minor work may take place away from the roadway. Note: the Vail Pass recreation path is not regularly maintained during the winter season. Regular maintenance will resume in the spring. 

Mountain Corridor: Golden to the Utah Border
New this winter season, CDOT has launched an online hub dedicated to the I-70 Mountain Corridor—a one-stop resource for winter driving information, road conditions, and tips for smooth, safe mountain travel. This resource brings together the best tools from COtrip.org and the COtrip Planner app in one centralized location: codot.gov/i70mountain.


 Anticipated Future Projects

  • First Bank, 17 Vail Road
  • East Lionshead Residence, 534 E. Lionshead Circle 

Online Community Development Portal

Customers of the Community Development Department have access to a 24/7 online portal to submit applications for contractor registration and construction-related permits. The portal, at http://vail.onlinegovt.com/ also accepts planning applications for review by the Design Review Board and Planning Environmental Commission. In addition, residents can access the citizen portal to submit a code enforcement request or check to see the status of any permit activity in their neighborhood. To view frequently asked questions, visit http://www.vail.gov/online-services.

Email Notification Service for Contractors and Consultants

Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab at: https://public.govedelivery.com/accounts/COVAIL/subscriber/new?topic

Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for construction update emails as well as other topics, visit www.vail.gov/vailmail.

Return to full list >>