Weekly Construction Update, March 2

Post Date:03/02/2026 8:00 AM

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator  
970-390-4677 or 970-479-2198; lsandoval@vail.gov  

Holidays and Special Events (No Work Days)
Memorial Day Holiday, May 23 – 25 

Featured Projects

Dobson Arena Remodel
Crews have completed the demolition of the northwest deck, making an opening for the installation of large ice making machines. Crews have completed concrete pours on the southwest and southeast sides of the arena and continue to work on concrete pour on the new stadia seating, on the south side of the arena.  Crews have tightened up construction barriers and expect there will be no full-road closures through the ski season. The project is scheduled to be completed in the fall 2026. Contractor is Hyder McHugh Construction. Town of Vail contact is John King, 970-376-0949.  

 Concourse level deck detailing continues Crews demolished NW deck to install large ice machines. 


Timber Ridge Village
Modular units for the final building – Building C – start going into place today. Elsewhere on site, exterior painting begins on Building F, wood and stone siding is ongoing for Building G, garage level wall insulation continues for Building B, crews finish roof framing and start installing roof shingles for Building E, and interior unit patching and stitching continues for Building D. The Timber Ridge Village housing project consists of a 302-unit multifamily complex. Building F is expected to open in Spring 2026 and the entire project is planned for completion in October 2026. More information on the development and housing units can be found at www.timberridgevail.com. The developer is Triumph Development West, Coleman Wise, 970-401-5304. The site excavating contractor is Schofield Construction, Joe Haugen, 970-210-0020. The site construction contractor is Jack Hughes, Shaw Construction, 970-471-0448. Town of Vail contact is Leonard Sandoval, 970-390-4677.

 Crews finish roof framing and start installing roof shingles  Crews finish roof framing and start installing roof shingles
   

Southface Vail (formerly West Middle Creek) Housing Development, 351 N. Frontage Road
The first project tower crane is expected to arrive and be erected today. Crews are working on storm lines on the east side of the property, continue with micropile drilling for MSE walls, start pouring footings for CIP walls, and continue soil nail wall drilling, grouting, spray-facing, and architectural shotcrete. Shaw Construction contact is John Payne, 303-350-1373. Town of Vail contact is Jason Dietz, 970-479-2145.
 Crews work on storm lines on the east side of the property  Crews continue with micropile drilling for MSE walls


Here’s a recap of other construction projects currently underway in Vail.  

Vail Village

Vail Athletic Field 
Crews are finishing up foundation backfill and passed all inspections.  Work begins interior, subgrade plumbing for fixtures and toilets. Vail Recreation District contact is Scott O’Connell, 970-477-5264. 

The 62, 278 Hanson Ranch Road (formerly Los Amigos) 
Work includes complete renovation of the existing restaurant and prep kitchen and landscaping. Work is focused on interior work and new construction. Work will be ongoing through the winter months. Deliveries of materials will occur on Hanson Ranch Road/top of Bridge Street, morning hours only during the winter months as needed with Right-of-Way Permit approval only. All work is currently contained within the construction fence. The contractor is RA Nelson, Jonny Cohen, 970-471-9258.

816 Forest Road Entry Bridge
Work on the Forest Road duplexes continues, including the footers and building foundations, new access road and retaining walls. Approval has been granted for the use of the lower lot for staging materials and equipment. General Contractor is Mexamer Construction Group, Matt Anderson, 970-471-3459. Town of Vail contact is Leonard Sandoval, 970-390-4677. 


I-70 News

New this winter season, CDOT has launched an online hub dedicated to the I-70 Mountain Corridor—a one-stop resource for winter driving information, road conditions, and tips for smooth, safe mountain travel. This resource brings together the best tools from COtrip.org and the COtrip Planner app in one centralized location: codot.gov/i70mountain.


 Anticipated Future Projects

  • First Bank, 17 Vail Road
  • East Lionshead Residence, 534 E. Lionshead Circle 

Online Community Development Portal

Customers of the Community Development Department have access to a 24/7 online portal to submit applications for contractor registration and construction-related permits. The portal, at http://vail.onlinegovt.com/ also accepts planning applications for review by the Design Review Board and Planning Environmental Commission. In addition, residents can access the citizen portal to submit a code enforcement request or check to see the status of any permit activity in their neighborhood. To view frequently asked questions, visit http://www.vail.gov/online-services.

Email Notification Service for Contractors and Consultants

Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab at: https://public.govedelivery.com/accounts/COVAIL/subscriber/new?topic

Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for construction update emails as well as other topics, visit www.vail.gov/vailmail.

Return to full list >>