Weekly Construction Update, March 23

Post Date:03/23/2026 8:00 AM

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator  
970-390-4677 or 970-479-2198; lsandoval@vail.gov  

Holidays and Special Events (No Work Days)
Memorial Day Holiday, May 23 – 25
Gro Pro Mountain Games, June 4 – 7 
Vail Craft Beer Classic, June 12- 13
Independence Day Holiday, July 3 - 5 

Featured Projects

Dobson Arena Remodel
Work has reached the peak of the project, with all the trades active on site. Progress continues in the new stadium seating area and new deck lounge, including the concession area, drink rail and balcony. The ice-making machine has been placed in with a crane and the walls are now being built around the 17-ton machine. Crews have tightened up construction barriers and expect there will be no full-road closures through the ski season. The project is scheduled to be completed in the fall 2026. Contractor is Hyder McHugh Construction. Town of Vail contact is John King, 970-376-0949.  

 Work continues on Dobson's new deck with balcony and concession area  Worker builds wall around ice making machine, skid room


Timber Ridge Village
Last modular is placed with a crane at Timber RidgeConstruction activity maintains a steady pace across the site. This work is headlined by Building F where crews are progressing through garage-level mechanical electrical and plumbing (MEP) trim-in, painting, and flooring while simultaneously nearing completion on interior unit patch-and-stitch work. Exterior finishes for Building F also are moving toward a milestone as painting, caulking, and metal siding installation continue, allowing for the initial removal of scaffolding. Building G is advancing with exterior siding and garage MEP rough-ins, while Buildings B, E, and D focus on interior patch-and-stitch work alongside building-specific exterior finishes. Finally, at Building C, the team is finishing roof framing and preparing for inspections following the recent modular unit set. Building F is planned for opening in Spring 2026 and the entire development remains firmly on track for final delivery in October 2026. More information on the development and housing units can be found at www.timberridgevail.com. The developer is Triumph Development West, Coleman Wise, 970-401-5304. The site excavating contractor is Schofield Construction, Joe Haugen, 970-210-0020. The site construction contractor is Jack Hughes, Shaw Construction, 970-471-0448. Town of Vail contact is Leonard Sandoval, 970-390-4677.


Southface Vail (formerly West Middle Creek) Housing Development, 351 N. Frontage Road
The first tier of Soil Nail Wall 3 is formed and shotcrete facing begins, making way for second-tier excavation. The site remains a hub of material management with roughly 10,000 yards of processed soil on hand and ongoing boulder exports clearing the path for continued site work. Similar momentum is visible with concrete work with spread footer pours continuing and new contractors arriving on site to start forming concrete caps for mechanically stabilized earth (MSE) walls. At the base of the site, the team will be completing terracing work by the bus stop and preparing for the next round micropile drilling. Shaw Construction contact is John Payne, 303-350-1373. Town of Vail contact is Jason Dietz, 970-479-2145.

 Construction begins to go vertical at Southface  Drone: view of crane at Southface


Here’s a recap of other construction projects currently underway in Vail.  

Vail Village

Vail Athletic Field 
Interior back fill and compaction is underway.  Framing materials are scheduled to arrive this week with framing to follow.  Vail Recreation District contact is Scott O’Connell, 970-477-5264. 

The 62, 278 Hanson Ranch Road (formerly Los Amigos) 
Work includes complete renovation of the existing restaurant and prep kitchen and landscaping. Work is focused on interior work and new construction. Work will be ongoing through the winter months. Deliveries of materials will occur on Hanson Ranch Road/top of Bridge Street, morning hours only during the winter months as needed with Right-of-Way Permit approval only. All work is currently contained within the construction fence. The contractor is RA Nelson, Jonny Cohen, 970-471-9258.

816 Forest Road Entry Bridge
Work on the Forest Road duplexes continues, including the footers and building foundations, new access road and retaining walls. Approval has been granted for the use of the lower lot for staging materials and equipment. General Contractor is Mexamer Construction Group, Matt Anderson, 970-471-3459. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

 


I-70 News

New this winter season, CDOT has launched an online hub dedicated to the I-70 Mountain Corridor—a one-stop resource for winter driving information, road conditions, and tips for smooth, safe mountain travel. This resource brings together the best tools from COtrip.org and the COtrip Planner app in one centralized location: codot.gov/i70mountain.

I-70 West Vail Pass Auxiliary Lanes Project
Winter Hiatus - This project remains on winter hiatus and will resume this spring for a final expected construction. No lane closures are expected during the winter break, though minor work may take place away from the roadway. Note: the Vail Pass recreation path is not regularly maintained during the winter season. Regular maintenance will resume in the spring.


 Anticipated Future Projects

  • First Bank, 17 Vail Road
  • East Lionshead Residence, 534 E. Lionshead Circle 

Online Community Development Portal

Customers of the Community Development Department have access to a 24/7 online portal to submit applications for contractor registration and construction-related permits. The portal, at http://vail.onlinegovt.com/ also accepts planning applications for review by the Design Review Board and Planning Environmental Commission. In addition, residents can access the citizen portal to submit a code enforcement request or check to see the status of any permit activity in their neighborhood. To view frequently asked questions, visit http://www.vail.gov/online-services.

Email Notification Service for Contractors and Consultants