Weekly Construction Update, March 30
Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator
970-390-4677 or 970-479-2198; lsandoval@vail.gov
Holidays and Special Events (No Work Days)
Memorial Day Holiday, May 23 – 25
Gro Pro Mountain Games, June 4 – 7
Vail Craft Beer Classic, June 12- 13
Independence Day Holiday, July 3 - 5
Featured Projects
Dobson Arena Remodel
Ongoing work remains active across multiple fronts. Work continues on a new accessible ramp to the seating area. South concourse slab on metal deck reinforcing and penetration layout continues, exterior framing and sheathing are progressing, and arena bowl mechanical, electrical and plumbing (MEP) hangers and rough-in remain in full swing. Crews are preparing to begin northwest structural steel and completing stadia pour number four. Crews have tightened up construction barriers and expect there will be no full-road closures through the ski season. The project is scheduled to be completed in the fall 2026. Contractor is Hyder McHugh Construction. Town of Vail contact is John King, 970-376-0949.
| |
|
Timber Ridge Village
Construction activity remains active across all buildings and the broader site this week. Building F leads the highlights as it moves toward completion — crews have begun working through the first rounds of interior unit and common area punch lists, and garage parking striping is underway. On the exterior, scaffolding is coming down as stucco siding is finished, with paint, caulking, and metal siding installation still in progress. Building G is pushing forward on exteriors with wood and stone siding installation ongoing. Building B is advancing with wood and stucco siding progressing as well as photovoltaic system installation. At Building E, exterior patch-and-stitch is complete, and stone siding is wrapping up as crews start working on stucco and wood siding. Interior patch-and-stitch and mechanical, electrical and plumbing (MEP) garage rough-ins are continuing in parallel. Wood and stone siding work is also moving forward at Building D. On the sitework front, guardrail and backfill work begins along Lions Ridge Loop. Finally, a notable milestone for the project, the crane for modular unit installation is being removed. Building F is planned for opening in Spring 2026 and the entire development remains firmly on track for final delivery in October 2026. Read more on the development and housing units at Timber Ridge Village. The developer is Triumph Development West, Coleman Wise, 970-401-5304. The site excavating contractor is Schofield Construction, Joe Haugen, 970-210-0020. The site construction contractor is Jack Hughes, Shaw Construction, 970-471-0448. Town of Vail contact is Leonard Sandoval, 970-390-4677.
| |
|
Southface Vail (formerly West Middle Creek) Housing Development, 351 N. Frontage Road
Soil Nail Wall 3 continues to advance as the second lift of soil nails is installed and shotcrete spray is scheduled for early in the week. Concrete momentum carries forward with the continuous north footer pour progressing and additional spread footer and column pours planned to follow. At the base of the site, MSE wall work shifts to the west side of the bus stop while concrete cap work gets underway on the east side. Looking ahead, crews are preparing for the arrival of two tower cranes in April, with excavation, leveling pad pours, and surveying all in progress. Shaw Construction contact is John Payne, 303-350-1373. Town of Vail contact is Jason Dietz, 970-479-2145.
| |
|
Gore Creek Promenade
The Promenade is closed to the public to allow the area to dry out in preparation for spring construction. Minor work begins this week, with the installation of a small flagstone pad. Beginning the week of April 6, fencing will be reinstalled around the project area, and the new fire feature boulder will be set on the new flagstone pad. Major work begins the week of April 13. The park is expected to reopen June 26. Coleman Custom Homes contact is John Michael Cuccio, 225-754-2470. Town of Vail contact is Gregg Barrie, 970-390-3286.
Here’s a recap of other construction projects currently underway in Vail.
Vail Village
Vail Athletic Field
With interior subgrade plumbing and electrical complete and sill plate installation and exterior rough grade ongoing, the project goes vertical this week with steel and lumber materials on site. Vail Recreation District contact is Scott O’Connell, 970-477-5264.
The 62, 278 Hanson Ranch Road (formerly Los Amigos)
Work includes complete renovation of the existing restaurant and prep kitchen and landscaping. Work is focused on interior work and new construction. Work will be ongoing through the winter months. Deliveries of materials will occur on Hanson Ranch Road/top of Bridge Street, morning hours only during the winter months as needed with Right-of-Way Permit approval only. All work is currently contained within the construction fence. The contractor is RA Nelson, Jonny Cohen, 970-471-9258.
816 Forest Road Entry Bridge
Work on the Forest Road duplexes continues, including the footers and building foundations, new access road and retaining walls. Approval has been granted for the use of the lower lot for staging materials and equipment. General Contractor is Mexamer Construction Group, Matt Anderson, 970-471-3459. Town of Vail contact is Leonard Sandoval, 970-390-4677.
Outlying
Gore Valley Trail Shoulder Repairs near Cascade Village
Crews will be reconstructing approximately 50 feet of gravel shoulder along the edge of the Gore Valley Trail just east of the Cascade Skier Bridge. The work includes a small boulder wall, gravel shoulder and topsoil installation. The work may begin the week of March 30 or April 6 and should be completed in 10 working days. The trail width will be reduced, but it will remain open during the work. Contractor contact is Kenny Vickers, 970-471-3201. Town of Vail contact is Gregg Barrie, 970-390-3286.
I-70 News
CDOT has an online hub dedicated to the I-70 Mountain Corridor—a one-stop resource for winter driving information, road conditions, and tips for smooth, safe mountain travel. This resource brings together the best tools from COtrip.org and the COtrip Planner app in one centralized location: codot.gov/i70mountain.
I-70 West Vail Pass Auxiliary Lanes Project
Winter Hiatus - This project remains on winter hiatus and will resume this spring for a final expected construction. No lane closures are expected during the winter break, though minor work may take place away from the roadway. Note: the Vail Pass recreation path is not regularly maintained during the winter season. Regular maintenance will resume in the spring.
Anticipated Future Projects
- First Bank, 17 Vail Road
- East Lionshead Residence, 534 E. Lionshead Circle
Online Community Development Portal
Customers of the Community Development Department have access to a 24/7 online portal to submit applications for contractor registration and construction-related permits. The portal, at http://vail.onlinegovt.com/ also accepts planning applications for review by the Design Review Board and Planning Environmental Commission. In addition, residents can access the citizen portal to submit a code enforcement request or check to see the status of any permit activity in their neighborhood. To view frequently asked questions, visit http://www.vail.gov/online-services.
Email Notification Service for Contractors and Consultants
Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab at: https://public.govedelivery.com/accounts/COVAIL/subscriber/new?topic
Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for construction update emails as well as other topics, visit www.vail.gov/vailmail.