Weekly Construction Update, May 18

Post Date:05/18/2026 8:00 AM

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator  
970-390-4677 or 970-479-2198; lsandoval@vail.gov  

Holidays and Special Events (No Work Days)
Memorial Day Holiday, May 23 – 25
Gro Pro Mountain Games, June 4 – 7 
Vail Craft Beer Classic, June 12- 13
Independence Day Holiday, July 3 - 5 

Featured Projects

Dobson Arena Remodel
Roof insulated sheathing and hot-applied roofing are progressing. Crews continue importing rink sand in preparation for the ice slab system. Work continues on south event and concourse overhead work, and east storm operations continue with the bike path closure until Memorial Day Weekend. Construction is expected to be completed in fall. Contractor is Hyder McHugh Construction. Town of Vail contact is John King, 970-376-0949.  

Crew member works on Dobson South Entrance  Crew member works on fire proofing interior


Timber Ridge Village
Residents are moving into Buildings A and F. Building B exterior work is advancing this week, with stucco color coat completing on the north side and metal siding and exterior paint continuing. Solar panels are being installed on Building B, and elevator work is underway. At Building G, stucco and wood siding are progressing across multiple elevations with exterior paint and caulking getting started. Building E exterior patch and stitch is wrapping up, with stone veneer continuing and wood siding beginning on the west elevation. Buildings C and D advance on stone veneer, interior finishes, and mechanical rough-in, with Building D’s front entry roof framing also underway. Xcel Energy’s gas service connections are active across the site. Site work is busy with curb and gutter, road base, trash enclosure foundations, and excavation for the western public staircase all moving forward. The full development remains on track for final delivery in Fall 2026.  For more information on the development and housing units, visit Timber Ridge Village. The developer is Triumph Development West, Coleman Wise, 970-401-5304. The site excavating contractor is Schofield Construction, Joe Haugen, 970-210-0020. The site construction contractor is Jack Hughes, Shaw Construction, 970-471-0448. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Crew member carries wood panel  Siding work at a Timber Ridge building


Southface Vail (formerly West Middle Creek) Housing Development, 351 N. Frontage Road
Soil nail wall work steps up to the third tier, with excavation and drilling getting underway while the second-tier perimeter drain wraps up. Foundation concrete work pushes forward across the full building footprint, with shotcrete, continuous footers, and spread footings rolling through the central and eastern portions of the building in sequence. The joint utility trench is moving along, with gas, electrical, and telecom all going into the ground this week. MEP underground rough-in for the first slab-on-grade pour is also beginning, keeping the building’s first concrete floor pour on track for later this month. Shaw Construction contact is John Payne, 303-350-1373. Town of Vail contact is Jason Dietz, 970-479-2145.  

Southface wall going up  Crew member in tractor works on MSE wall


Gore Creek Promenade
Crews continue to haul out excess soil, install drainage systems, and build boulder walls.  Crews are excavating and installing paver walkways and flagstone paving. The team is preparing to place sod this week to allow for a 5-to-6-week establishment period before opening the park to the public. Work hours are 7 a.m. to 7 p.m. Monday through Saturday. The park is closed for the work and is expected to reopen June 26.  Coleman Custom Homes contact is John Michael Cuccio, 225-754-2470.  Town of Vail contact is Gregg Barrie, 970-390-3286. 

Crews haul out excess soil  Crews work on building boulder walls


Here’s a recap of other construction projects currently underway in Vail.  

Vail Village

10th Mountain Division Memorial Landscape Renewal
Work includes the installation of a 750-square-foot stone patio and associated site work around the 10th Mountain Division Statue located near the Vail Covered Bridge. The project includes removal of existing flagstone, installation of natural stone paving, boulders, minor electrical work, and landscape improvements including planting and irrigation. The area will be fenced. The estimated completion date is June 1. Contractor is Rocky Mountain Custom Landscapes, Matt Krigman, 970-904-9906. Town of Vail Contact is Kim White, 970-343-9259.

298 Hanson Ranch Road, New Deck Improvements  
Work includes new deck and exterior improvements. Construction staging and fencing will be within the Town of Vail right-of-way but not on the street. Expect single-lane closure as needed for material delivery on Hanson Ranch Road with permit approval between 7 and 8:30 a.m. only. Completion date is scheduled for July 29.  Contractor is McAuther Enterprises, 970-977-0113. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

The 62, 278 Hanson Ranch Road (formerly Los Amigos) 
Work includes complete renovation of the existing restaurant and prep kitchen and landscaping. Work is focused on interior work and new construction. A crane is on site but will not affect access. Deliveries of materials will occur on Hanson Ranch Road/top of Bridge Street. All work is currently contained within the construction fence. The contractor is RA Nelson, Jonny Cohen, 970-471-9258.

230 Bridge St. (Slifer Building)
Work includes exterior remodel, new stairs, windows and paint. Fencing will be added around the project before GoPro events. Completion of the project is June 19. Contractor is D G Construction, 970-390-5840. Town of Vail contact is Leonard Sandoval, 970-390-4677. 
 
816 Forest Road Entry Bridge
Work on the Forest Road duplexes continues, including the footers and building foundations, new access road and retaining walls. Approval has been granted for the use of the lower lot for staging materials and equipment. General Contractor is Mexamer Construction Group, Matt Anderson, 970-471-3459. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

420 S. Frontage Road, Xcel Energy 
Completion of Phase 2 has begun. Traffic lanes and sidewalk on the S. Frontage Road will be narrowed during daylight working hours. Completion of work is scheduled for June 19. Xcel Energy contact is Marc Mayorga, 303-653-2346. 

720 S. Frontage Road E
Town of Vail utility work includes burying above ground power lines. Initial work will begin on Spraddle Creek Rd, will continue to S. Frontage Road at Ford Park Parking Lot, then through TOV Shops to Bald Mountain Road. Traffic control will be provided. Completion of project is estimated in August. Contractor is Mason Sweaney, 307-7512-4911. Town of Vail contact is Chad Salli, 970-376-2389.


Outlying

Holy Cross Energy Spraddle Creek Underground  
Construction crews begin installing infrastructure to relocate the existing overhead electrical lines north of I-70 from Spraddle Creek to Bald Mountain Road underground.  Work will begin on the S. Frontage Rd. from Elkhorn Dr. to Aspen Ln.  Expect single lane closures with flaggers during working hours. Work hours are 7 a.m. - 7 p.m. Monday-Saturday.  Contractor is Advanced Electrical Contracting from Sheridan, Wyoming. Town of Vail contact is Chad Salli, 970-376-2389.
 
Lions Ridge Loop Rockfall Fencing
Crews continue the rockfall fencing above Lions Ridge Loop. Lions Ridge Loop will be closed from behind Timber Ridge Village to Savoy Villas to all traffic (vehicular, pedestrian and bicycle) to facilitate the installation of the fencing foundations and netting. Town of Vail contact is Chad Salli, 970-376-2389.

Vail Athletic Field
 

Work is on schedule with both interior and exterior framing.  Roof has been dried in, and the rooms are starting to take shape.  Crews are preparing to install a new fire hydrant to protect the new structure and will cap a 30-year-old abandoned irrigation line that once helped establish trees planted on the east side of the sand volleyball courts.  Safety fence is also being reinstalled to protect the structure and the Athletic field from tee shots on hole 6. Vail Recreation District contact is Scott O’Connell, 970-477-5264.  

Vail Tank 4 Project
Eagle River Water & Sanitation District is completing a multi-year rehabilitation project on the below-grade water tank on Potato Patch Drive. Trucks and other heavy equipment will be parked on the side of the road and activities may occasionally require traffic to travel in the opposite direction of the normal flow on Potato Patch Drive. Traffic control will be in place as needed throughout the project. The ERWSD contact is Dan Duerr, 970-333-6773.

Main Gore Place Watermain Improvements
Eagle River Water & Sanitation District will perform waterline replacements in the Gore Creek Meadows community located at 5020 Main Gore PL., in East Vail. The Racquet Club Townhomes, Gore Creek Meadows and Sundial Communities will experience truck and heavy equipment traffic, as well as infrequent water shutdowns which will be communicated prior to taking place. Traffic control will be in place as needed throughout the project. Impacts to public roadways is expected to be minimal. The ERWSD contact is Dan Duerr, 970-333-6773.

Booth Falls, 3035 Booth Falls Rd.
Eagle River Water & Sanitation District will perform emergency power upgrades to the facility located above the Booth Falls Trailhead. Pedestrian access will be maintained from the service gate to the trailhead. Improvements involve grading and clearing for a generator pad and electrical trenching on the service road up to the upper water treatment facility. Following that work, a standby generator and rock fall fence will be installed to provide power to critical pumping and treatment facilities during an extended power outage. The ERWSD contact is Dan Duerr, 970-333-6773.


I-70 News

Gypsum to Eagle resurfacing 
CDOT starts a resurfacing project today from Gypsum to Eagle. Daytime work hours are 7 a.m. to 7 p.m. Monday through Thursday and 7 a.m. to 12 p.m. Friday. Nighttime work hours are 7 p.m. to 7 a.m. Sunday through Friday. Minimal delays are expected. Traffic impacts include single-lane closures, 11-foot width restriction and a speed reduction to 55 mph. For details and updates, visit CDOT’s dedicated I-70 Mountain Corridor page, a one-stop resource for construction information, road conditions, and tips for smooth, safe mountain travel.  

I-70 West Vail Pass Auxiliary Lanes Project
This is the last phase of this project. Minor holds are expected in small windows.  Motorists should anticipate, this month, traffic will be shifted to the south into a head-to-head, barrier separated alignment in the new eastbound lanes to allow for roadway and wildlife underpass construction. Sign up for Vail Pass Auxiliary Lanes project updates, emails and webcams. For text alerts about the project, text 'vailpass' (one word, lowercase) to 21000. 

 


 Anticipated Future Projects

  • 315 Mill Creek Circle new SFR (Spring 2026)
  • 728 W. Lionshead Circle, Ritz Carlton deck and stucco repairs (Spring 2026)
  • 17 Vail Road, FirstBank redevelopment (Fall 2026)
  • 281 Bridge Street, Bridge Street Condos addition (Fall 2026)
  • 292 E. Meadow Drive, Mountain Haus new entry (Fall 2026)
  • 400 Vail Valley Drive new stairs to stream walk (Fall 2026)
  • 534 E. Lionshead Circle, Lionshead Residences redevelopment (Fall 2026)
  • 250 S. Frontage Road, Evergreen redevelopment (Spring 2027)
  • 304 Bridge Street, Red Lion redevelopment (Spring 2027)
  • 616 W. Lionshead Circle, Concert Hall Plaza redevelopment (Spring 2027)

     


Online Community Development Portal

Customers of the Community Development Department have access to a 24/7 Town of Vail Application and Permitting Portal to submit applications for contractor registration and construction-related permits.

Email Notification Service for Contractors and Consultants

Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab.

Do you know of others who would be interested in receiving construction updates from the Town of Vail? Sign up for construction update emails.

Return to full list >>