Weekly Construction Update, July 20

Post Date:07/20/2026 8:00 AM

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator  
970-390-4677 or 970-479-2198; lsandoval@vail.gov  

Holidays and Special Events (No Work Days)
Vail Kids Adventure Games, (Vail Village) Aug. 6 – 9
Vail Fine Arts Show, (Lionshead) Aug. 13 - 16
Labor Day Weekend - Sept. 5 – 7

Featured Projects

Dobson Arena Remodel
Mechanical crews continue roof-top unit rough-in activities while installing the remaining HVAC equipment throughout the facility. Civil work on the west storm system also continues to progress. The west vestibule is transforming as parallel panels go up in the ceiling and painters continue black dryfall painting applications. Roofing operations remain focused on the standing seam roof installation, and interior crews are progressing drywall work within the administration area. Door installation and hardware continue throughout the building, while all mechanical, electrical and plumbing (MEP) trades are actively performing trim-out work. Crews are in the final stages of painting walls throughout the facility, installing gutters, and beginning stadia seating installation. Dobson Arena is on track for its grand opening celebration in November.  Contractor is Hyder McHugh Construction. Town of Vail contact is John King, 970-376-0949.

 New railing installed on second floor deck  New railing installed on second floor deck


Timber Ridge Village
Timber Ridge Village construction keeps rolling into the back half of July, with steady progress across both sitework and building exteriors. Along the North Frontage Road, crews finish curb and gutter work at the bus loop and move into final prep for the bus loop driveway. On the west half of the site, curb and gutter work outside the fence is completed, trash enclosure framing and siding continue, and crews begin re-grading the slope near Building A's west stairs ahead of paving, with asphalt paving still on track for the last week of July. Building A continues its irrigation and landscaping work. Building B continues gutter and downspout installation on the exterior, while mechanical and electrical rough-in work in the garage level is completed. Building C moves from stucco into wood siding this week, starting on the west elevation and shifting to the south elevation by week's end, while stone veneer work continues on the north and east sides. Building D continues wood siding work, shifting toward the west elevation, and crews begin connecting the elevator generator. Building E has a busy week — stucco continues on the east and north elevations, metal siding gets underway, and crews begin generator hookup work, while inside, garage-level mechanical and electrical work is completed and elevator installation begins. Building G continues exterior paint and caulking as painters finish detail work on the south side following last week's siding completion, while the final unit interior touch-ups continue in the garage level. For more information on the development and housing units, visit Timber Ridge Village. The developer is Triumph Development West, Coleman Wise, 970-401-5304. The site excavating contractor is Schofield Construction, Joe Haugen, 970-210-0020. The site construction contractor is Jack Hughes, Shaw Construction, 970-471-0448. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

 Scolfolding on the last of the Timber Ridge buildings  Exterior work on the final Timbe Ridge building


Southface Vail (formerly West Middle Creek) Housing Development, 351 N. Frontage Road
This week, crews begin building out several rooms inside the parking garage — including the snow melt, trash, and electrical rooms — with concrete block walls going up as interior work kicks off on both parking levels. Concrete work also remains a major focus: the first pour of the upper-floor concrete deck, on the east end of the building, is being finished out with wall and column work, cable tensioning, waterproofing, and a protective spray coating, while preparation begins for the next deck pour moving toward the center of the building. At ground level, floor work continues moving westward through the building, with the ground being leveled and slabs poured in some areas while underground plumbing and electrical lines are put in ahead of the next section. Retaining wall work remains active across the site — soil backfilling is wrapping up on the poured concrete wall, construction continues on the engineered block retaining wall, and crews continue drilling and anchoring the hillside with steel rods on the north side of the site. Wall and column work also continues at the west end of the building — the final section in this phase of work — with the last part being built and poured this week.  Shaw Construction contact is John Payne, 303-350-1373. Town of Vail contact is Jason Dietz, 970-479-2145.   

Level one of Southface errected  


Here’s a recap of other construction projects currently underway in Vail.  

Vail Village

298 Hanson Ranch Road - Base Camp  
Work includes new deck and exterior improvements. Construction staging is contained within fencing and screen. Expect single-lane closure as needed for material delivery on Hanson Ranch Road with permit approval between 7 and 8:30 a.m. only. Completion date is scheduled for end of July.  Contractor is McAuther Enterprises, 970-977-0113. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

The 62, 278 Hanson Ranch Road (formerly Los Amigos) 
Work includes complete renovation of the existing restaurant and prep kitchen and landscaping. Work is focused on interior work and new construction. Deliveries of materials will occur on Hanson Ranch Road/top of Bridge Street, morning hours only during the winter months as needed with Right-of-Way Permit approval only. All work is currently contained within the construction fence. The contractor is RA Nelson, Jonny Cohen, 970-471-9258.

281 Bridge Street - (condo building)
Work includes resurfacing, roof replacement and internal remodel. Contractor is Burke Larson, Vail Custom Homes, 970-390-3188. Town of Vail contact is Leonard Sandoval, 970-479-2198.

816 Forest Road Entry Bridge
Work on the Forest Road duplexes continues, including the footers and building foundations, new access road and retaining walls. Approval has been granted for the use of the lower lot for staging materials and equipment. General Contractor is Mexamer Construction Group, Matt Anderson, 970-471-3459. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

720 S. Frontage Road E
Town of Vail utility work includes burying above ground power lines. Initial work will begin on Spraddle Creek Rd, will continue to S. Frontage Road at Ford Park Parking Lot, then through TOV Shops to Bald Mountain Road.  Expect lane closure in July. Traffic control will be provided. Completion of project is estimated in August. Contractor is Mason Sweaney, 307-7512-4911. Town of Vail contact is Chad Salli, 970-376-2389.

Outlying

Dowd Junction, Gore Valley Trail
Use caution on the trail just east of the deer crossing fence. Town of Vail crews have cordoned off a small section in one lane of the path to work on severe cracks and hole in the pavement. Pedestrians and bikes can get by. Town of Vail Contact is Chad Salli, 970-376-2389.

Holy Cross Energy Spraddle Creek Underground  
Work has begun installing electrical infrastructure in the Bald Mountain Neighborhood behind the berm. Crews have been installing infrastructure to relocate the existing overhead electrical lines north of I-70 from Spraddle Creek to Bald Mountain Road underground.  Work is ongoing at S. Frontage Road from Elkhorn Drive to Aspen Lane.  Expect single lane closures with flaggers during working hours and 24-hour closure of the eastbound Frontage Road shoulder to facilitate the work. Work hours are 7 a.m. - 7 p.m., Monday – Saturday. Contractor is Advanced Electrical Contracting from Sheridan, Wyoming. Town of Vail contact is Chad Salli, 970-376-2389. 

Vail Tank 4 Project
Eagle River Water & Sanitation District is completing a multi-year rehabilitation project on the below-grade water tank on Potato Patch Drive. Trucks and other heavy equipment will be parked on the side of the road and activities may occasionally require traffic to travel in the opposite direction of the normal flow on Potato Patch Drive. Traffic control will be in place as needed throughout the project. Work could go through October. The ERWSD contact is Dan Duerr, 970-333-6773.  


Main Gore Place Watermain Improvements
Eagle River Water & Sanitation District is performing waterline replacements in the Gore Creek Meadows community located at 5020 Main Gore PL, in East Vail.  The Racquet Club Townhomes, Gore Creek Meadows, and Sundial Communities will be experiencing truck and heavy equipment traffic, as well as infrequent water shutdowns which will be communicated prior to taking place. Traffic control will be in place as needed throughout the project. Impacts to public roadways is expected to be minimal. The project is on track to be completed at the end of August. The ERWSD contact is Dan Duerr, 970-333-6773.  

Booth Falls, 3035 Booth Falls Rd.
Eagle River Water & Sanitation District is performing emergency power upgrades to the facility located above the Booth Falls Trailhead (3035 Booth Falls Rd.) Pedestrian access will be maintained from the service gate to the trailhead. Rockfall fence work is ongoing. Improvements will involve grading and clearing for a generator pad, and electrical trenching on the service road up to our upper water treatment facility. Following that work, a standby generator and rock fall fence will be installed to provide power to critical pumping and treatment facilities during an extended power outage. Work is expected to continue through September. The ERWSD contact is Dan Duerr, 970-333-6773.  

I-70 News

Gypsum to Eagle resurfacing 
CDOT is resurfacing from Gypsum to Eagle now through November. Daytime work hours are 7 a.m. to 7 p.m. Monday through Thursday and 7 a.m. to 12 p.m. Friday. Nighttime work hours are 7 p.m. to 7 a.m. Sunday through Friday. Daily lane closures between Gypsum to Eagle. Nightly bridge work east of Eagle, near Wolcott. Minimal delays are expected. Traffic impacts include single-lane closures, 11-foot width restriction and a speed reduction to 55 mph. For details and updates, visit CDOT’s dedicated I-70 Mountain Corridor page, a one-stop resource for construction information, road conditions, and tips for smooth, safe mountain travel.  

I-70 West Vail Pass Auxiliary Lanes Project

The window for helicopter operations requiring traffic holds runs from mid-June to early September. Only a few total traffic hold days are anticipated during this time to move equipment in and out of the area. The traffic holds will last for about 20 minutes in both directions, but delays could be longer as the queues are cleared. Night work is possible at the start of the season and is expected to be more consistent beginning this summer through the project’s completion. The nearby recreation path is expected to remain open and unaffected. For real-time updates, check COtrip Planner App, COtrip.org, or text "vailpass" to 21000. 


 Anticipated Future Projects

  • 17 Vail Road, FirstBank – Redevelopment (Fall 2026)
  • 281 Bridge Street, Bridge Street Condos – Addition (Fall 2026)
  • 292 E. Meadow Drive, Mountain Haus – New Entry (Fall 2026)
  • 400 Vail Valley Drive – New stairs to stream walk (Fall 2026)
  • 534 E. Lionshead Circle, Lionshead Residences – Redevelopment (Fall 2026)
  • 304 Bridge Street, Red Lion – Redevelopment (Spring 2027)
  • 250 S. Frontage Road, Evergreen – Redevelopment (Spring 2027)
  • 616 W. Lionshead Circle, Concert Hall Plaza – Redevelopment (Spring 2027)

Online Community Development Portal

Customers of the Community Development Department have access to a 24/7 Town of Vail Application and Permitting Portal to submit applications for contractor registration and construction-related permits.

Email Notification Service for Contractors and Consultants

Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab.

Do you know of others who would be interested in receiving construction updates from the Town of Vail? Sign up for construction update emails.

Return to full list >>