Weekly Construction Update, Aug. 24

Post Date:08/24/2026 8:00 AM

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator  
970-390-4677 or 970-479-2198; lsandoval@vail.gov  

Holidays and Special Events (No Work Days)
Vail Farmers Market/Art Show, (Sundays) June 14 through October 11 
Labor Day Weekend – Sept. 5 - 7 
Vail Social (Vail Village), Sept. 8 
Vail Oktoberfest, (Lionshead) – Sept. 11 - 13 (Vail Village) – Sept. 18 – 20  

Featured Projects

Dobson Arena Remodel

Dobson wrapped a busy few weeks with 20 different crews and over 100 workers onsite. The big current themes are paint, electronics and ice with dryfall continuing throughout the building, speakers being wired and hung and the ice plant being brought online to cool the ice floor. Another exciting milestone: the scoreboards were hung on Thursday. Metal, stone and fascia continues to be applied to the exterior and landscape walls are being installed. The plumbing system is being chlorinated. Contractor is Hyder McHugh Construction. Town of Vail contact is John King, 970-376-0949. Dobson Arena is on track to begin programming and host a grand opening celebration in November. Contractor is Hyder McHugh Construction. Town of Vail contact is John King, 970-376-0949.       

 The expansive Dobson Arena with two large green cranes installing speakers in the iconic ceiling Scoreboard at Dobson with new ceiling work visible
 Speakers being installed  The new scoreboard was installed Thursday


Timber Ridge Village

Timber Ridge Village keeps up a steady pace this week, with progress visible across the site and several buildings. Sidewalk pours continue near Buildings B and G, and Building A's south entry stair railings get installed and painted. Building B begins garage door installation this week. Building C continues wood siding on the south and east elevations, moving toward the north face as the week progresses. Building D continues stucco work on the east elevation. Building E has a busy week, with metal siding and generator connection work continuing on the exterior. The building's solar panel system goes in as well. Building G continues connecting its generator and moves into garage door work. Look for continued sidewalk work and steady exterior progress across the buildings, as the future bus stop moves closer to completion.

For more information on the development and available housing units, visit Timber Ridge Village.

The developer is Triumph Development West, Coleman Wise, 970-401-5304. The site excavating contractor is Schofield Construction, Joe Haugen, 970-210-0020. The site construction contractor is Jack Hughes, Shaw Construction, 970-471-0448. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

 The exterior of Timber Ridge with buildings at different phases of construction with a mountain visible behind and blue sky


Southface Vail (formerly West Middle Creek) Housing Development, 351 N. Frontage Road

This week at Southface Vail marks a big milestone: the first concrete pour on the building's third floor happens Monday. Curing, form removal, and cable tensioning follow through the rest of the week. Much of the work this week reflects a pattern that's been building all summer — crews complete one section of the building before shifting to the next, moving steadily across the structure from east to west. On the second floor, that means column and wall work wraps up on last week's deck section just as rebar and cable-tensioning work picks up on the next one. At the west end, that same progression brings the last footing and column work on the ground floor to a close this week, with the final piece of that structural work starting right behind it. On the hillside retaining wall to the north, the sequence continues too: crews install the drain behind the completed wall section while excavation begins on the next section further along.  Shaw Construction contact is John Payne, 303-350-1373. Town of Vail contact is Jason Dietz, 970-479-2145. 

Drone image of Southface site with cranes visible on a moody, cloud covered day  Floor work being laid for cement pour at Southface


Vail Nature Center In-Stream Restoration 

In-stream excavation for the partnership project between Town of Vail, Trout Unlimited and Colorado Parks and Wildlife will begin on Monday, August 10 and continue through September 30. Work will begin at the upstream end of the project reach closest to the property boundary with the Golf Course. Construction access will be from Vail Valley Drive down the access road to the Nature Center. Town of Vail Contact is Pete Wadden, 970-568-6753. Frontier Environmental contact is Javier Mares 720-297-1240. 


 

Here’s a recap of other construction projects currently underway in Vail.  

Vail Village

298 Hanson Ranch Road - Base Camp  
Work includes new deck and exterior improvements. Construction staging is contained within fencing and screen. Expect single-lane closure as needed for material delivery on Hanson Ranch Road with permit approval between 7 and 8:30 a.m. only. Completion date is scheduled for late-August/early September 2026. Contractor is McAuther Enterprises, 970-977-0113. Town of Vail contact is Leonard Sandoval, 970-390-4677.   

The 62, 278 Hanson Ranch Road (formerly Los Amigos) 
Work includes complete renovation of the existing restaurant and prep kitchen and landscaping. Work is focused on interior work and new construction. Deliveries of materials will occur on Hanson Ranch Road/top of Bridge Street, morning hours only during the summer months as needed with Right-of-Way Permit approval only. All work is currently contained within the construction fence. Projected completion in November. The contractor is RA Nelson, Matt Johanningmeier, 970-401-0430.

17 Vail Road, PNC Bank/Prima Residences Project. 
Complete demo and new construction of commercial and residential units. Interior of building is currently being vacated. Construction start date is yet TBD, pending Building Permit approval. Contractor is Saunders Inc., Reno Romagnoli, 845-420-8910. Town of Vail Contact is Leonard Sandoval, 970-390-4677.
 
281 Bridge Street - (condo building)
Work includes resurfacing, roof replacement and internal remodel. Use of Gore Creek Drive for trash removal and material delivery to occur, Monday – Thursday, 7 to 8:30 a.m. as needed during the summer months. Projected completion is late December. Contractor is Burke Larson, Vail Custom Homes, 970-390-3188. Town of Vail contact is Leonard Sandoval, 970-479-2198.

292 E. Meadow Drive, Mountain Haus – New Entry 
Start Date on exterior work yet TBD. Contractor, DBK Construction & Services Solutions, 389-215-2719.  Town of Vail contact is Leonard Sandoval, 970-390-4677 
 
816 Forest Road Entry Bridge
Work on the Forest Road duplexes continues, including the footers and building foundations, new access road and retaining walls. Approval has been granted for the use of the lower lot for staging materials and equipment. General Contractor is Mexamer Construction Group, Matt Anderson, 970-471-3459. Town of Vail contact is Leonard Sandoval, 970-390-4677.  
 
720 S. Frontage Road E - TOV utility work

Town of Vail utility work includes burying above ground power lines. Asphalt restoration of the Frontage Road is complete, crews will begin shouldering and striping the week of 8/10. Installation of electrical conduit and vaults continues north of I-70 from Spraddle Creek Road to the Public Works complex. Completion of project is estimated in September. Contractor is Mason Sweaney, 307-751-4911. Town of Vail contact is Chad Salli, 970-376-2389.

Lionshead  

500 E. Lionshead Circle. The Montelisse Project. Demolition of the Lions Pride Building  
Demolition start date is currently scheduled for September 15, 2026, completion of the work will take approximate 3 weeks. Construction/Excavation and shoring to follow pending approval of the building permit. Contractor is Hyder Construction, Doug Thompson, 303-829-5950, Town of Vail Contact is Leonard Sandoval, 970-390-4677. 

Outlying

North Recreation Path Improvements 

Starting after Labor Day, the Town of Vail will begin the North Recreation Path Improvements project. The project limits are from the Pedestrian Overpass to Vail Run. Work consists of the construction of a new pedestrian bridge over Red Sandstone Creek, realignment of the pedestrian crossings to enhance safety for path users, and path resurfacing. A separated pedestrian detour will be set up along the N. Frontage Road for the duration of the project. The expected completion date is November 15, 2026. Town of Vail contact is Chris Delles 970-477-3418. 

Dowd Junction, Gore Valley Trail
Use caution when walking or cycling just east of the deer crossing screen. Vail Public Works crews have fenced off cracked pavement on one side of the path for safety and will make repairs. Pedestrians and bikes can get by. Town of Vail Contact is Chad Salli, 970-376-2389.
 
Vail Athletic Field  

Exterior finishes are underway with several elements nearing completion.  Stucco work is now complete, colored concrete pour is also complete.  Exterior staining of wood elements is nearing completion.  Garage and entry doors are installed.  Roofers are on site preparing for the installation of the live material.  Rough grade around the perimeter is also nearing completion.  Interior elements are also nearing completion with electrical, HVAC, and plumbing trim out underway.  We are preparing to pull primary power cable from our new transformer to the building on Tuesday August 25th.  We can then prepare to energize the new building which will be a major milestone.  Final coordination with the TOV is underway for the replacement of the asphalt parking lot and the installation of a new fire hydrant.  We will also schedule the removal of an old irrigation line that dates back to the mid 1980’s. Vail Recreation District contact is Scott O’Connell, 970-477-5264.  

Holy Cross Energy Spraddle Creek Underground  
Eagle River Water & Sanitation District is completing a multi-year rehabilitation project on the below-grade water tank on Potato Patch Drive. Trucks and other heavy equipment will be parked on the side of the road and activities may occasionally require traffic to travel in the opposite direction of the normal flow on Potato Patch Drive. Traffic control will be in place as needed throughout the project. Work could go through October. The ERWSD contact is Dan Duerr, 970-333-6773.  

Vail Tank 4 Project
Eagle River Water & Sanitation District is completing a multi-year rehabilitation project on the below-grade water tank on Potato Patch Drive. Trucks and other heavy equipment will be parked on the side of the road and activities may occasionally require traffic to travel in the opposite direction of the normal flow on Potato Patch Drive. Traffic control will be in place as needed throughout the project. Work could go through October. The ERWSD contact is Dan Duerr, 970-333-6773.  


Main Gore Place Watermain Improvements
Eagle River Water & Sanitation District is performing waterline replacements in the Gore Creek Meadows community located at 5020 Main Gore PL, in East Vail.  The Racquet Club Townhomes, Gore Creek Meadows, and Sundial Communities will be experiencing truck and heavy equipment traffic, as well as infrequent water shutdowns which will be communicated prior to taking place. Traffic control will be in place as needed throughout the project. Impacts to public roadways is expected to be minimal. The project is on track to be completed at the end of August. The ERWSD contact is Dan Duerr, 970-333-6773.   

Booth Falls, 3035 Booth Falls Rd.
Eagle River Water & Sanitation District is performing emergency power upgrades to the facility located above the Booth Falls Trailhead (3035 Booth Falls Rd.) Pedestrian access will be maintained from the service gate to the trailhead. Ongoing activities include excavation and concrete work for a generator pad and electrical trenching across the service road to the transformer West of the parking area. Following that work, a standby generator will be installed to provide power to critical pumping and treatment facilities during extended power outages. Work is expected to continue through September 2026. The ERWSD contact is Dan Duerr, 970-333-6773.  

West Vail Water Main Improvements   
Eagle River Water & Sanitation District (ERWSD) is beginning an infrastructure improvement project in the West Vail Matterhorn neighborhood. This work will replace aging water and sanitary sewer mains along Geneva Drive, along with new water and sewer service lines connecting to the upgraded main. 

This investment will ensure reliable water and sewer service for the community for decades to come. Construction will begin in August 2026 and will pause for the winter season, resuming in spring 2027. The project is expected to be completed by the end of 2027. Residents should expect temporary water outages and traffic impacts along Geneva Drive, Matterhorn Circle, and Upper Matterhorn Circle during construction. ERWSD will provide advanced notice to residents before any scheduled outage. We appreciate the community's patience as we work to minimize disruption while completing this essential upgrade. The ERWSD contact is Mark Mantua at 970-401-0822. 

I-70 News

I-70 West Vail Pass Auxiliary Lanes Project
Westbound I-70 
Various single-lane closures are possible between Vail Pass and East Vail, Mile Points 190 and 180, from 5 a.m. to 10 p.m. each day starting Monday, Aug. 24, through Friday, Aug. 28. Single-lane closures are also possible the morning of Saturday, Aug. 29, from 5 a.m. to 9 a.m. No night work is scheduled this week. 
  
Eastbound I-70 
Various single-lane closures are possible between East Vail and Vail Pass, Mile Points 180 and 190, from 5 a.m. to 5 p.m. each day starting Monday, Aug. 24, through Friday, Aug. 28. Single-lane closures are also possible the morning of Saturday, Aug. 29, from 5 a.m. to 9 a.m. No night work is scheduled this week. 

For real-time updates, check COtrip Planner App, COtrip.org, or text "vailpass" to 21000. 


 Anticipated Future Projects

  • 400 Vail Valley Drive – New stairs to stream walk (Fall 2026)
  • 304 Bridge Street, Red Lion – Redevelopment (Spring 2027)
  • 250 S. Frontage Road, Evergreen – Redevelopment (Spring 2027)
  • 616 W. Lionshead Circle, Concert Hall Plaza – Redevelopment (Spring 2027)

Online Community Development Portal

Customers of the Community Development Department have access to a 24/7 Town of Vail Application and Permitting Portal to submit applications for contractor registration and construction-related permits.

Email Notification Service for Contractors and Consultants

Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab.

Do you know of others who would be interested in receiving construction updates from the Town of Vail? Sign up for construction update emails.

Return to full list >>